What are the debugging steps for a new fully automatic slag discharge centrifugal separation filter

Source:www.tonglvda.com      Release date: 2026-11-04
1、 Pre debugging preparation and pre inspection
1. Data and installation verification
Verify the equipment qualification certificate, nameplate parameters (rated flow rate, operating speed, separation factor, design pressure, material), electrical schematic diagram, and PLC program version; Confirm that the secondary grouting and solidification of the equipment foundation are completed, the anchor bolts are tightened, and the levelness meets the manufacturer's requirements; The direction of the inlet and outlet pipes, overflow pipes, slag discharge pipes, flushing water pipes, and sewage pipes is correct, the support is fixed in place, and there is no forced docking force.
2. Lubrication and mechanical inspection
Add bearing lubricating grease/oil according to the instruction manual, with the oil level within the specified range; Manually rotate the drum, ensuring smooth rotation without any jamming or friction noise, and confirming that there is no collision or friction between the drum and the casing; Check that the slag discharge piston, sealing components, and flushing nozzle are not damaged or bumped.
3. Inspection of pneumatic/hydraulic drive system (hydraulic slag discharge machine type)
The slag discharge drive water source pipeline is flushed clean, and the filter is free of impurities; The calibration of the pressure regulating valve and pressure gauge is qualified; Flexible opening and closing of valves; Adjust the driving water pressure to the initial range given by the manufacturer (usually 0.4-0.6MPa, depending on the model); Explosion proof models are verified to have reliable electrical and grounding connections, and the grounding resistance meets the standard.
4. Electrical and self-control inspection
Confirm that the power supply voltage and phase sequence are correct; The wiring of the emergency stop button, vibration switch, temperature sensor, and liquid level/pressure differential sensor is correct; PLC、 Touch screen communication is normal; Safety interlocks (over vibration interlock, over temperature interlock, hood safety interlock) should be tested separately first, and the equipment should be immediately shut down after triggering. If the interlock fails, it is prohibited to proceed to the next step of debugging.
5. On site protection confirmation
The slag discharge outlet and rotating parts have complete protective barriers/covers; The slag collection box is in place, and the flow of waste liquid is unobstructed; Prepare clean water, tools, thermometers, vibrometers, and tachometers on site.
2、 No load debugging (no medium or material input)
Purpose: To verify the stability, vibration, temperature rise, and automatic slag discharge mechanism operation logic of the host
1. Start the motor first and confirm that the direction of rotation is consistent with the marked arrow. It is strictly prohibited to turn on the machine if the direction is incorrect.
2. Start the host to run without load and gradually increase it to the set speed (for variable frequency models, slowly increase the speed to avoid resonance range); Continuous no-load operation for no less than 30 minutes.
3. Monitoring records: bearing seat temperature, vibration speed, and abnormal noise of the machine body; After the bearing temperature stabilizes, the temperature rise generally does not exceed 40K and the temperature does not exceed 70 ℃; The vibration value is within the manufacturer's allowable range.
4. Test manual slag discharge mode separately: manually trigger slag discharge on the touch screen, observe the stroke and opening/closing timing of the slag discharge piston, and ensure that the action is smooth without impact or jamming; After the slag discharge is completed, the piston is reset to its original position.
5. Basic settings for debugging self-control parameters: Set the timed slag discharge duration, pressure difference slag discharge threshold, slag discharge holding time, flushing duration, and slag discharge interval lock time in the PLC; Confirm that the two slag discharge modes can be activated separately or linked together.
6. No load shutdown test: Normal shutdown process, emergency shutdown action, and no abnormal impact during the shutdown process.
Abnormalities during the no-load phase: excessive vibration, abnormal noise, rapid temperature rise of bearings, and inadequate operation of the slag discharge mechanism. Immediately stop the machine for troubleshooting and prohibit water ingress and material carrying.
3、 Clear water linkage debugging (water flow without solid particles)
Purpose: To verify the timing of fluid system, flushing system, pipeline leakage, and automatic circulation
1. Close the feed valve and turn on the clean water supply. First, pre flush the feed pipeline and internal flow channel to remove residual welding slag and debris during installation.
2. Turn on the feed water and gradually adjust the frequency of the feed valve/feed pump according to the design flow rate, first reducing the flow rate and then increasing it to the rated flow rate; Observe the status of the overflow port, and ensure that the overflow pipeline is unobstructed without any pressure buildup.
3. Check the sealing points of the entire machine: the sealing surface of the machine seal, flange, and slag discharge piston, without any external leakage or dripping; Observe the water outlet status of the flushing nozzle, distribute water evenly, and effectively flush the inner wall of the drum.
4. Enter automatic mode and verify the complete cycle: feeding → separation standby → triggering slag discharge → slag discharge accompanied by flushing → slag discharge end reset, the entire timing logic is correct; Check that the clear water is discharged smoothly during slag discharge, without backflow or water hammer in the pipeline.
5. Calibration feedback sensor: For differential pressure control models, check the zero point of the differential pressure under clear water conditions; Liquid level linkage control review liquid level signal feedback.
6. Operate stably under clean water conditions for no less than 60 minutes, and record flow rate, pressure, speed, temperature, and vibration data.
4、 Trial operation and debugging with materials (medium containing solid phase, simulating actual working conditions)
This step is the core debugging of the cutting fluid purification scenario. It is recommended to start with low solid content materials
1. Material preparation: Use the actual medium to be processed on site (cutting fluid/grinding fluid), and control the initial solid content near the lower limit of the design solid content to avoid instantaneous slag accumulation and overload.
2. Slowly cut in the material, stabilize the feed flow rate, and maintain consistency with the flow rate of clean water debugging; Observe the clear state of the clear liquid outlet.
3. Verify the slag discharge logic by mode:
Timed slag discharge mode: automatic slag discharge after observing the set time, and smooth discharge of slag slurry; Evaluate the solid content of slag discharge and the proportion of slag discharge wastewater;
Differential pressure slag discharge mode: As the filter cake accumulates inside the drum, the differential pressure slowly increases and automatically triggers slag discharge when it reaches the set threshold; Adjust the pressure difference threshold or slag discharge interval based on the actual speed of slag accumulation;
4. Parameter optimization:
Quick slag accumulation and frequent slag discharge: the triggering pressure difference can be appropriately increased, or the solid content of incoming materials can be checked for exceeding the standard;
Unclean slag discharge and excessive residue: prolong the slag discharge holding time, adjust the flushing water pressure and flushing duration;
Slag discharge brings out a large amount of clear liquid: reduces the driving pressure of slag discharge and shortens the opening time of slag discharge;
5. Continuous and stable operation with material: Run continuously for 2-4 hours, take samples every half hour to test the cleanliness of the clear liquid; Synchronize and continuously monitor vibration, bearing temperature, and seal leakage.
6. Verify boundary conditions: observe equipment adaptability with slight fluctuations in feed flow rate; Check if the overflow protection is functioning properly.
5、 Interlock protection and alarm function review (review during the material stage)
Simulate triggering in sequence: vibration exceeding limit, bearing over temperature, hood opening, emergency stop, feeding high pressure alarm, confirm that the equipment is reliably shut down, and record the alarm on the touch screen; Confirmed alarm information can be uploaded to SCADA/MES (if available).
6、 Shutdown program verification and parameter solidification
1. Test standard shutdown process: stop feeding → delay flushing of the drum → empty the medium inside the machine → slow down and shut down the main engine; It is forbidden to leave slag in the drum for a long time.
2. Organize and archive the confirmed rotational speed, feed flow rate, slag discharge pressure, slag discharge timing, pressure difference threshold, and flushing parameters as the benchmark parameters for equipment operation, and deliver them to maintenance.
3. Clean up the site, collect debugging slag samples, and compare the cleanliness of the liquid before and after debugging.
7、 Debugging acceptance and data transfer
1. Organize and debug record forms: no-load records, clear water records, operating parameters with materials, alarm test records, cleanliness detection data;
2. Provide instructions to the operators and maintenance personnel of the user: key points for normal inspections, common alarm meanings, prohibited operation items, and regular maintenance plans;
3. Sign the debugging order and the equipment will be put into normal production and use.